Drainage
& Flood Control |
Scottsdale Road,
Frank Lloyd Wright Boulevard to Thompson Peak
Parkway - Segment 1
Scottsdale,
Arizona
Dibble provided pavement
and drainage analysis and design for the reconstruction
of approximately ½ mile of Scottsdale
Road and a portion of Mayo Boulevard in the
vicinity of the Loop 101 Freeway. The drainage
component of the project included extensive
off-site hydrology data collection and both
onsite and offsite stormwater runoff design.
A culvert and channel conveyance system is
provided to transport 100-year stormwater
runoff safely from the Loop 101 Freeway through
a Lund Cadillac commercial property, adjacent
to Scottsdale Road and Mayo Boulevard. The
pavement drainage component of the project
included complete design for a 10-year storm
event, including approximately ½ mile
of new underground storm drain. Construction
was completed in 2005.
|
|