Water
Resources |
Bullard Avenue Sanitary
Sewer -
Lower Buckeye Parkway to Elwood Street
Goodyear,
Arizona
Dibble, as the design
engineer for the City of Goodyear's Design-Build
Team, provided design and construction phase
services for approximately 6,250 linear feet
of 36-inch interceptor sewer and 660 linear
feet of 24-inch sanitary sewer. The new sewer,
located along Bullard Avenue between Lower
Buckeye Parkway and Elwood Street, completes
an important link in the City's regional sewer
collection system.
Comprehensive stakeholder
coordination was critical to the success of
the project; including coordination with multiple
municipal agencies, the Roosevelt Irrigation
District, and multiple adjacent private and
public developers associated with the construction
of the City's Spring Training Baseball Complex.
The project schedule was
dictated by the City of Goodyear's commitment
to have the Spring Training Baseball Complex
completed by Fall
|
|